Water
Chestnut removal timeline
There's a lot
of things to think about before a project can
begin.
Disposal:
Roger wrote waste disposal officials three months
before the removal could start.
Permits:
Roger needed approval from the agencies that
own the water body. Samples provided at right
for the benefit of others who want to start
similar projects. Each request included a proposal,
dates that the project would happen, and explicit
request for what the project needs from them.

|
Permits
needed
Permit outcome
The project was
issued a Negative DOA (Determination Of Applicability)[of
the WPA] by Conservation Commissions, but had
OOC's (Order Of Conditions) issued by two of
the Commissions to further guide harvesting.