Water Chestnut removal timeline

There's a lot of things to think about before a project can begin.

Disposal: Roger wrote waste disposal officials three months before the removal could start.

Permits: Roger needed approval from the agencies that own the water body. Samples provided at right for the benefit of others who want to start similar projects. Each request included a proposal, dates that the project would happen, and explicit request for what the project needs from them.

Permits needed

Permit outcome

The project was issued a Negative DOA (Determination Of Applicability)[of the WPA] by Conservation Commissions, but had OOC's (Order Of Conditions) issued by two of the Commissions to further guide harvesting.